THE AVARE KL CONDOMINIUM,JALAN TUN RAZAK, K.L.
All cracks appear on beam and slab are sealed and re-bonded the crack section with low viscosity resin using the twin line injection system.
Very low viscosity resin & twin line resin dispenser pump ensure good penetration to hairlines cracks.
Total cracks sealed more than 3 kilometers.
4-STOREY BUILDING (EX-PARKSON),KEPONG BARU
All cracks on roof were sealed with epoxy injection. Defective concrete was removed and surface was roughened by UHP Water-jet System.
Apply waterproofing and top with protective screed.
Refurbishment by: Liquid applied, elastomeric seamless water-proofing membrane, top finish with screed and elastomeric cold tar bitumen sealant.
1MG RESERVOIR, GENTING HIGHLANDS
The reservoir had to be completely drained and cleaned by wet sandblasting. Cracks had to be mapped & sealed by pressure injection of low viscosity resin and spalled and porous areas treated with polymer modified repair mortar.
Finally, the total area was protected with a seamless and flexible cementitious waterproofing system.
The total surface area – including pillars, was treated with Smart flex after repaired.
CHEMICAL WASTE TREATMENT PLANT, KUALITI ALAM
Corrosion Protective Coating System To Structural Steel
Due to the high acidic environment, all the existing structural steel started to form rust and existing coating peel-off from the substrate.
The management requested ecological method to remove the existing paint and re-coat with Corrosion Protective Coating System.
RAMP A & B, KLIA INTERCHANGE, KM31.6 SOUTH BOUND, SECTION 6, NORTH-SOUTH EXPRESSWAY CENTRAL LINK
Installation of Whisper Grip On Road Pavement.
Due to the ramps were lead to frequent accidents, PLUS has requested to install the Anti-Skid system to prevent or reduce the accidents.
Ever since the installation of Whisper Grip system, the recorded number of accidents has substantially reduced.